Tealing Airfield PV (31 MW)
Tealing Airfield PV is a 31 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 11 December 2017; the record was last updated on 4 April 2018.
31 MWsolar farm
permission expiredstatus in REPD
4 April 2018record last updated
Anguscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 May 2014 | Application submitted |
| 11 December 2014 | Planning permission granted |
| 11 December 2017 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 31 MW
- Status (REPD)
- permission expired
- Record last updated
- 4 April 2018
- Operator or applicant
- Green Cat Renewables
- Planning authority
- Angus
- Planning application reference
- 14/00428/FULM
- Site area
- 51.2 ha
- Address (REPD)
- Former Airfield, Tealing, Dundee, Angus
- Council area (by location)
- Angus
- Time to decision
- 28 weeks
- REPD reference
- 2295
Who decides
| Applications | Angus | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 72 | 10,236 |
| Refused | 21 (29%) | 19% |
| Solar refused | 1 of 36 | 12% |
| Onshore wind refused | 18 of 19 | 45% |
| Battery storage refused | 2 of 17 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Balnuith Farm, Tealing | battery storage | 100 | approved, not built | 1.1 |
| Field 279M North East of 15 Tealing | solar farm | 5 | abandoned | 1.7 |
| Tealing Solar Energy Park - Phase 2 | solar farm | 110 | approved, not built | 2.7 |
| Pitkerro Road | battery storage | 49.9 | refused | 4.8 |
| Templeton Farm, Templeton | battery storage | 49.9 | approved, not built | 5.0 |
| Dunsinane Industrial Estate | battery storage | 49.9 | operational | 5.1 |
| New Craigie Retail Park | battery storage | 50 | approved, not built | 5.4 |
| Tealing Battery Energy Storage Farm | battery storage | 80 | approved, not built | 5.5 |
| Frawney Wind Farm | wind farm | 9.2 | refused | 5.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5199, -2.9711).