Field 279M North East of 15 Tealing (5 MW solar farm)

Field 279M North East of 15 Tealing is a 5 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 20 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
20 October 2017record last updated
Anguscouncil area

Planning timeline

DateStage
20 April 2015Application submitted
3 November 2015Planning permission granted
5 November 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
20 October 2017
Operator or applicant
Green Power Consultants
Planning authority
Angus
Planning application reference
15/00331/FULL
Site area
9.3 ha
Address (REPD)
Field 270M North East Of, 15, Tealing, Dundee, Tayside
Council area (by location)
Angus
Time to decision
28 weeks
REPD reference
5160

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Balnuith Farm, Tealingbattery storage100approved, not built1.4
Tealing Airfield PVsolar farm31permission expired1.7
Tealing Solar Energy Park - Phase 2solar farm110approved, not built1.7
Frawney Wind Farmwind farm9.2refused3.9
Dodd Hillwind farm12.5refused on appeal4.5
Wellbank Solar Farmsolar farm25approved, not built5.3
Tealing Battery Energy Storage Farmbattery storage80approved, not built5.4
Pitkerro Roadbattery storage49.9refused5.8
Ark Hill Wind Farmwind farm9.2application submitted6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5333, -2.9588).