Tealing Solar Energy Park - Phase 2 (110 MW)

Tealing Solar Energy Park - Phase 2 is a 110 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 March 2025, not yet built; the record was last updated on 8 April 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

110 MWsolar farm
approved, not builtstatus in REPD
8 April 2025record last updated
Anguscouncil area

Planning timeline

DateStage
17 November 2023Application submitted
25 March 2025Section 36 consent granted (Scottish Ministers)
25 March 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
110 MW
Status (REPD)
approved, not built
Record last updated
8 April 2025
Operator or applicant
Sirius EcoDev Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004882
Address (REPD)
N/O Leyshade, Tealing, Dundee
Council area (by location)
Angus
Time to decision
71 weeks
REPD reference
14543

Recorded together with Tealing Battery Energy Storage Farm (80 MW battery storage, approved, not built).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Tealing Solar Energy Park - Phase 2 ECU0000488211017 November 2023approved on 25 March 2025, not yet built

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Field 279M North East of 15 Tealingsolar farm5abandoned1.7
Tealing Airfield PVsolar farm31permission expired2.7
Balnuith Farm, Tealingbattery storage100approved, not built3.0
Dodd Hillwind farm12.5refused on appeal3.1
Wellbank Solar Farmsolar farm25approved, not built3.5
Frawney Wind Farmwind farm9.2refused4.4
Pitkerro Roadbattery storage49.9refused5.2
New Craigie Retail Parkbattery storage50approved, not built6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5303, -2.9309).