Ark Hill Wind Farm (9.2 MW)
Ark Hill Wind Farm is a 9.2 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 21 October 2021, no decision recorded; the record was last updated on 29 October 2021. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.
The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.
Planning timeline
| Date | Stage |
|---|---|
| 21 October 2021 | Application submitted |
Project details
- Technology
- wind farm
- Capacity
- 9.2 MW
- Status (REPD)
- application submitted
- Record last updated
- 29 October 2021
- Operator or applicant
- Ark Hill Wind Farm 2 Limited
- Planning authority
- Angus
- Planning application reference
- 21/00765/EIAL
- Address (REPD)
- Ark Hill Wind Farm, Glen Ogilvie, Glamis, Forfar
- Council area (by location)
- Angus
- REPD reference
- 9864
Who decides
| Applications | Angus | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 72 | 10,236 |
| Refused | 21 (29%) | 19% |
| Solar refused | 1 of 36 | 12% |
| Onshore wind refused | 18 of 19 | 45% |
| Battery storage refused | 2 of 17 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Ark Hill | wind farm | 6.4 | operational | 1.0 |
| Balnuith Farm, Tealing | battery storage | 100 | approved, not built | 5.5 |
| Frawney Wind Farm | wind farm | 9.2 | refused | 5.8 |
| Field 279M North East of 15 Tealing | solar farm | 5 | abandoned | 6.1 |
| Tealing Airfield PV | solar farm | 31 | permission expired | 6.5 |
| Templeton Farm, Templeton | battery storage | 49.9 | approved, not built | 6.5 |
| Tealing Solar Energy Park - Phase 2 | solar farm | 110 | approved, not built | 7.8 |
| Pyotdykes Farm, Stoneygroves, Liff Solar Farm | solar farm | 28 | approved, not built | 8.1 |
| Haughend Farm - Alyth Battery Energy Storage System | battery storage | 900 | approved, not built | 8.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.562, -3.0443).