Ark Hill Wind Farm (9.2 MW)

Ark Hill Wind Farm is a 9.2 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 21 October 2021, no decision recorded; the record was last updated on 29 October 2021. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
application submittedmay be out of datestatus in REPD
29 October 2021record last updated
Anguscouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
21 October 2021Application submitted

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
application submitted
Record last updated
29 October 2021
Operator or applicant
Ark Hill Wind Farm 2 Limited
Planning authority
Angus
Planning application reference
21/00765/EIAL
Address (REPD)
Ark Hill Wind Farm, Glen Ogilvie, Glamis, Forfar
Council area (by location)
Angus
REPD reference
9864

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ark Hillwind farm6.4operational1.0
Balnuith Farm, Tealingbattery storage100approved, not built5.5
Frawney Wind Farmwind farm9.2refused5.8
Field 279M North East of 15 Tealingsolar farm5abandoned6.1
Tealing Airfield PVsolar farm31permission expired6.5
Templeton Farm, Templetonbattery storage49.9approved, not built6.5
Tealing Solar Energy Park - Phase 2solar farm110approved, not built7.8
Pyotdykes Farm, Stoneygroves, Liff Solar Farmsolar farm28approved, not built8.1
Haughend Farm - Alyth Battery Energy Storage Systembattery storage900approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.562, -3.0443).