Pyotdykes Farm, Stoneygroves, Liff Solar Farm (28 MW)

Pyotdykes Farm, Stoneygroves, Liff Solar Farm is a 28 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 March 2024, not yet built; the record was last updated on 8 October 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWsolar farm
approved, not builtstatus in REPD
8 October 2024record last updated
Anguscouncil area

Planning timeline

DateStage
25 October 2023Application submitted
13 March 2024Planning permission granted
13 March 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
28 MW
Status (REPD)
approved, not built
Record last updated
8 October 2024
Operator or applicant
Sonnedix Weston Limited
Planning authority
Angus
Planning application reference
23/00756/FULM
Site area
30.0 ha
Address (REPD)
500M East Of Stoneygroves Liff
Council area (by location)
Angus
Time to decision
20 weeks
Contracts for Difference
AR6
Name in REPD
Pyotdykes Farm, Stoneygroves, Liff - Solar Farm
REPD reference
11847

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Templeton Farm, Templetonbattery storage49.9approved, not built1.8
Dundee Technology Parkbattery storage49.9operational2.0
Grange Of Berryhill Solar Farmsolar farm49.9approved, not built2.9
Dunsinane Industrial Estatebattery storage49.9operational3.1
Dormitories Star Inn Farm, Mains Of Fowlisbattery storage49.9approved, not built3.7
Locarno Works, Brown Streetbattery storage39.9approved, not built5.8
Tealing Airfield PVsolar farm31permission expired6.4
Balnuith Farm, Tealingbattery storage100approved, not built6.6
Field 279M North East of 15 Tealingsolar farm5abandoned7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4893, -3.0598).