Energy Projects Near You

Templeton Farm, Templeton (49.9 MW battery storage)

Templeton Farm, Templeton is a 49.9 MW battery storage project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 November 2024, not yet built; the record was last updated on 10 December 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
10 December 2024record last updated
Anguscouncil area

Planning timeline

DateStage
15 March 2024Application submitted
21 November 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
10 December 2024
Operator or applicant
Fig Power
Planning authority
Angus
Planning application reference
24/00095/FULM
Address (REPD)
200M West Of Templeton Farm Templeton Birkhill
Council area (by location)
Angus
Time to decision
36 weeks
Name in REPD
Templeton Farm, Templeton - Battery Storage
REPD reference
13605

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pyotdykes Farm, Stoneygroves, Liff Solar Farmsolar farm28approved, not built1.8
Dunsinane Industrial Estatebattery storage49.9operational3.3
Dundee Technology Parkbattery storage49.9operational3.5
Grange Of Berryhill Solar Farmsolar farm49.9approved, not built3.9
Balnuith Farm, Tealingbattery storage100approved, not built4.9
Tealing Airfield PVsolar farm31permission expired5.0
Dormitories Star Inn Farm, Mains Of Fowlisbattery storage49.9approved, not built5.4
Locarno Works, Brown Streetbattery storage39.9approved, not built6.1
Field 279M North East of 15 Tealingsolar farm5abandoned6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5031, -3.0459).