Dunsinane Industrial Estate (49.9 MW battery storage)

Dunsinane Industrial Estate is a 49.9 MW battery storage project in Dundee City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 3 May 2023; the record was last updated on 16 May 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
operationalstatus in REPD
16 May 2023record last updated
Dundee Citycouncil area

Planning timeline

DateStage
2 December 2019Application submitted
18 February 2022Planning permission granted
3 May 2023Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
16 May 2023
Operator or applicant
JLEN Environmental Assets Group
Planning authority
Dundee City
Planning application reference
19/00876/FULL
Address (REPD)
Land To The W/O Kinnoull Stree, Dunsinane Avenue, Dunsinane Industrial Estate, Dundee, Tayside
Council area (by location)
Dundee City
Time to decision
116 weeks
REPD reference
7591

Who decides

ApplicationsDundee CityUK
Decided applications (solar, wind, battery)1210,236
Refused2 (17%)19%
Solar refused1 of 612%
Onshore wind refused0 of 145%
Battery storage refused1 of 516%
Median time from submission to decision24.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grange Of Berryhill Solar Farmsolar farm49.9approved, not built1.5
Dundee Technology Parkbattery storage49.9operational2.7
Locarno Works, Brown Streetbattery storage39.9approved, not built2.9
Pyotdykes Farm, Stoneygroves, Liff Solar Farmsolar farm28approved, not built3.1
Templeton Farm, Templetonbattery storage49.9approved, not built3.3
New Craigie Retail Parkbattery storage50approved, not built4.9
Tealing Airfield PVsolar farm31permission expired5.1
Pitkerro Roadbattery storage49.9refused5.3
Dormitories Star Inn Farm, Mains Of Fowlisbattery storage49.9approved, not built5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4803, -3.0124).