Land To The West Of Kirkton Barns Farm (5 MW solar farm)

Land To The West Of Kirkton Barns Farm is a 5 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 27 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
27 September 2018record last updated
Fifecouncil area

Planning timeline

DateStage
17 April 2015Application submitted
9 October 2015Planning permission granted
9 October 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
27 September 2018
Operator or applicant
Green Power Consultants
Planning authority
Fife
Planning application reference
15/00545/FULL
Site area
10.3 ha
Address (REPD)
Land To The West Of, Kirkton Barns Farm, Tayport
Council area (by location)
Fife
Time to decision
25 weeks
REPD reference
5326

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Craigie Retail Parkbattery storage50approved, not built6.1
Locarno Works, Brown Streetbattery storage39.9approved, not built6.5
Pitkerro Roadbattery storage49.9refused6.8
Dunsinane Industrial Estatebattery storage49.9operational9.4
Tealing Battery Energy Storage Farmbattery storage80approved, not built9.4
Grange Of Berryhill Solar Farmsolar farm49.9approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4247, -2.8973).