Glaxo Smith Kline Wind Turbine (5 MW)
Glaxo Smith Kline Wind Turbine is a 5 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 August 2012; the record was last updated on 27 September 2012.
5 MWwind farm
refusedstatus in REPD
27 September 2012record last updated
Anguscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 14 December 2011 | Application submitted |
| 29 August 2012 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 5 MW
- Status (REPD)
- refused
- Record last updated
- 27 September 2012
- Operator or applicant
- WSP Environmental
- Planning authority
- Angus
- Planning application reference
- 11/01184/EIAL
- Turbines
- 2
- Address (REPD)
- Site 2 & 3 Cobden Street Montrose
- Council area (by location)
- Angus
- Time to decision
- 37 weeks
- REPD reference
- 2819
Who decides
| Applications | Angus | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 72 | 10,236 |
| Refused | 21 (29%) | 19% |
| Solar refused | 1 of 36 | 12% |
| Onshore wind refused | 18 of 19 | 45% |
| Battery storage refused | 2 of 17 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Dunmill, Substation Dun | battery storage | 49.9 | approved, not built | 6.4 |
| Balwyllo Farm, Dun Energy Storage Facility | battery storage | 50 | approved, not built | 6.5 |
| East Ballochy | solar farm | 39.9 | approved, not built | 6.9 |
| Mount Boy | wind farm | 6 | refused on appeal | 7.8 |
| Arrats Mill, Arrat | solar farm | 18.5 | approved, not built | 8.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.7059, -2.4551).