Energy Projects Near You

Glaxo Smith Kline Wind Turbine (5 MW)

Glaxo Smith Kline Wind Turbine is a 5 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 August 2012; the record was last updated on 27 September 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
refusedstatus in REPD
27 September 2012record last updated
Anguscouncil area

Planning timeline

DateStage
14 December 2011Application submitted
29 August 2012Refused by the planning authority

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
27 September 2012
Operator or applicant
WSP Environmental
Planning authority
Angus
Planning application reference
11/01184/EIAL
Turbines
2
Address (REPD)
Site 2 & 3 Cobden Street Montrose
Council area (by location)
Angus
Time to decision
37 weeks
REPD reference
2819

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunmill, Substation Dunbattery storage49.9approved, not built6.4
Balwyllo Farm, Dun Energy Storage Facilitybattery storage50approved, not built6.5
East Ballochysolar farm39.9approved, not built6.9
Mount Boywind farm6refused on appeal7.8
Arrats Mill, Arratsolar farm18.5approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.7059, -2.4551).