Lodge Hill (6.9 MW wind farm)

Lodge Hill is a 6.9 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 June 2014; the record was last updated on 16 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
refusedstatus in REPD
16 July 2014record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
11 June 2012Application submitted
6 June 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
refused
Record last updated
16 July 2014
Operator or applicant
Vento Ludens
Planning authority
Aberdeenshire
Planning application reference
APP/2012/1971
Turbines
3
Address (REPD)
Lodge Hill, Boyndie, Banff, Grampian
Council area (by location)
Aberdeenshire
Time to decision
104 weeks
REPD reference
4212

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Boyndie Airfieldwind farm16.7operational3.9
Stoneyhillwind farm30.6application withdrawn4.5
Denheadsolar farm25approved, not built4.9
Deuchrieswind farm6.9operational5.5
Brownside Farm - Electricity Production Facility & Battery Storagesolar farm35approved, not built9.0
Lurg Hill Wind Farmwind farm15approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6327, -2.6643).