Energy Projects Near You

Boyndie Airfield (16.7 MW wind farm)

Boyndie Airfield is a 16.7 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2006; the record was last updated on 28 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.7 MWwind farm
operationalstatus in REPD
28 June 2016record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
24 June 2003Application submitted
23 July 2004Planning permission granted
1 September 2005Construction started
1 February 2006Operational

Project details

Technology
wind farm
Capacity
16.7 MW
Status (REPD)
operational
Record last updated
28 June 2016
Operator or applicant
RDC Scotland Ltd/ Falck Renewables
Planning authority
Aberdeenshire
Planning application reference
APP/2003/1692
Turbines
8
Address (REPD)
Boyndie Airfield, Banff
Council area (by location)
Aberdeenshire
Time to decision
56 weeks
REPD reference
4671

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lodge Hillwind farm6.9refused3.9
Denheadsolar farm25approved, not built4.1
Stoneyhillwind farm30.6application withdrawn6.1
Law Of Doune Road, Macduffbattery storage49.9approved, not built8.2
Deuchrieswind farm6.9operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6653, -2.639).