Energy Projects Near You

Deuchries (6.9 MW wind farm)

Deuchries is a 6.9 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2017; the record was last updated on 2 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
operationalstatus in REPD
2 October 2018record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
13 November 2012Application submitted
17 April 2014Planning permission granted
31 August 2017Construction started
15 December 2017Operational

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
operational
Record last updated
2 October 2018
Operator or applicant
Force 9 Energy / Catamount Energy/ Green Cat
Planning authority
Aberdeenshire
Planning application reference
APP/2012/3229
Turbines
3
Address (REPD)
Deuchries Farm, Banff, Aberdeenshire
Council area (by location)
Aberdeenshire
Time to decision
74 weeks
REPD reference
4360

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stoneyhillwind farm30.6application withdrawn3.0
Brownside Farm - Electricity Production Facility & Battery Storagesolar farm35approved, not built4.0
Lodge Hillwind farm6.9refused5.5
Denheadsolar farm25approved, not built6.1
Boyndie Airfieldwind farm16.7operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5907, -2.6157).