Energy Projects Near You

Clashindarroch (37 MW wind farm)

Clashindarroch is a 37 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 June 2015; the record was last updated on 29 June 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37 MWwind farm
operationalstatus in REPD
29 June 2015record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
1 June 2009Application submitted
14 December 2010Planning permission granted
1 June 2013Construction started
26 June 2015Operational

Project details

Technology
wind farm
Capacity
37 MW
Status (REPD)
operational
Record last updated
29 June 2015
Operator or applicant
Vattenfall
Planning authority
Aberdeenshire
Planning application reference
APP/2009/1380
Turbines
18
Address (REPD)
Clashindarroch Forest, Huntly,
Council area (by location)
Aberdeenshire
Time to decision
80 weeks
REPD reference
4623

Earlier applications for this site

ApplicationMWSubmittedOutcome
Clashindarroch IEC3/6712918 August 2003refused 1 May 2006

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clashindarroch 2wind farm77approved, not built4.5
Clashindarroch Wind Farm Extensionwind farm139approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3665, -2.8661).