A981 Fraserburgh (45 MW battery storage)

A981 Fraserburgh is a 45 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 April 2023, not yet built; the record was last updated on 3 July 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWbattery storage
approved, not builtstatus in REPD
3 July 2023record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
7 February 2023Application submitted
13 April 2023Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
45 MW
Status (REPD)
approved, not built
Record last updated
3 July 2023
Operator or applicant
Fraserburgh Energy Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2023/0193
Address (REPD)
East Of A981
Council area (by location)
Aberdeenshire
Time to decision
9 weeks
Name in REPD
A981 Fraserburgh - Battery Energy Storage
REPD reference
12711

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mormond Hill Windfarmwind farm27.6refused on appeal2.7
Solar Panels at Clayfords Farmsolar farm6approved, not built2.8
Electricity Sub Station, Strichenbattery storage50approved, not built3.4
House O'Hillwind farm5operational4.3
Strichen Northbattery storage25abandoned4.5
Strichen Southbattery storage10abandoned6.2
Fraserburgh Developmentbattery storage25permission expired8.7
Greenbank Caravan & Trailers, Hillhead Of Phingaskbattery storage50approved, not built9.0
Smiddyhill, Strichenbattery storage49.9application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6072, -2.1099).