Energy Projects Near You

Solar Panels at Clayfords Farm (6 MW)

Solar Panels at Clayfords Farm is a 6 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 November 2024, not yet built; the record was last updated on 26 November 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
approved, not builtstatus in REPD
26 November 2024record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
9 August 2024Application submitted
19 November 2024Planning permission granted

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
approved, not built
Record last updated
26 November 2024
Operator or applicant
Solar Farm Number 2
Planning authority
Aberdeenshire
Planning application reference
APP/2024/1169
Site area
9.0 ha
Address (REPD)
Clayfords Farm, W/O Clayfords Cottages, Strichen, Fraserburgh
Council area (by location)
Aberdeenshire
Time to decision
15 weeks
Name in REPD
Strichen Solar Project, Clayfords Farm - Solar Panels
REPD reference
17030

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Electricity Sub Station, Strichenbattery storage50approved, not built1.6
Mormond Hill Windfarmwind farm27.6refused on appeal2.1
A981 Fraserburghbattery storage45approved, not built2.8
Strichen Northbattery storage25abandoned2.9
Strichen Southbattery storage10abandoned4.2
House O'Hillwind farm5operational5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5847, -2.09).