Energy Projects Near You

Hill of Fiddes (6.9 MW wind farm)

Hill of Fiddes is a 6.9 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 February 2010; the record was last updated on 9 May 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
operationalstatus in REPD
9 May 2012record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
3 September 2007Application submitted
1 April 2008Planning permission granted
1 July 2009Construction started
20 February 2010Operational

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
operational
Record last updated
9 May 2012
Operator or applicant
Infinis, previously Broadview Energy
Planning authority
Aberdeenshire
Planning application reference
APP/2007/3578
Turbines
3
Address (REPD)
Hill of Fiddes Udny Station Cultercullen
Council area (by location)
Aberdeenshire
Time to decision
30 weeks
REPD reference
3968

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kincraig Solar Farm and battery storage systemsolar farm21under construction2.8
Mains of Cairnbrogiewind farm9.2refused on appeal9.1
Middleton Of Potterton Farmbattery storage49.9approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3109, -2.1096).