Energy Projects Near You

Middleton Of Potterton Farm (49.9 MW battery storage)

Middleton Of Potterton Farm is a 49.9 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 July 2025, not yet built; the record was last updated on 29 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
29 July 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
12 June 2024Application submitted
9 July 2025Planning permission granted
9 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
Green Switch Capital (Qair)
Planning authority
Aberdeenshire
Planning application reference
APP/2025/0313
Address (REPD)
Middleton Of Potterton Farm, Aberdeen
Council area (by location)
Aberdeenshire
Time to decision
56 weeks
Name in REPD
Middleton Of Potterton Farm - Battery Energy Storage System
REPD reference
17259

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower Bodachrasolar farm72approved, not built3.7
Aryburn Farm, Dycebattery storage49.9refused4.2
Farburn Placebattery storage30under construction5.6
Persley Croftbattery storage49.9approved, not built5.7
Dyce Energy Storage, Raiths Industrial Estate Battery Facilitybattery storage50operational5.8
Persley BESSbattery storage70approved, not built6.0
Aberdeen Hydrogen Hub Facilitysolar farm8abandoned8.3
Hill of Fiddeswind farm6.9operational9.3
A981 Fraserburghbattery storage25approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2275, -2.1099).