A981 Fraserburgh (25 MW battery storage)

A981 Fraserburgh is a 25 MW battery storage project in Aberdeen City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 February 2022, not yet built; the record was last updated on 28 February 2022. REPD also records that the planning permission expired on 21 February 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
approved, not builtmay be out of datestatus in REPD
28 February 2022record last updated
Aberdeen Citycouncil area

REPD also records that the planning permission expired on 21 February 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
23 December 2021Application submitted
21 February 2022Planning permission granted
21 February 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
28 February 2022
Operator or applicant
Fraserburgh Energy Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2021/2855
Address (REPD)
E/O A981 Fraserburgh
Council area (by location)
Aberdeen City
Time to decision
9 weeks
Name in REPD
A981 Fraserburgh - Battery Energy Storage
REPD reference
10222

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Aberdeen Hydrogen Hub Facilitysolar farm8abandoned1.7
Newton Of Pitfodelsbattery storage40approved, not built2.4
Craigshaw Drive Battery Storage Facility & Electric Vehicle Charging Hubbattery storage20approved, not built3.6
Persley BESSbattery storage70approved, not built4.3
Persley Croftbattery storage49.9approved, not built4.5
Bankhead Recycling Solar Array, Battery Storage & Hydrogenbattery storage5approved, not built5.9
Rigifa Cove Roadbattery storage49.9approved, not built6.0
Lower Bodachrasolar farm72approved, not built7.3
Farburn Placebattery storage30under construction7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1408, -2.1401).