Energy Projects Near You

Newton Of Pitfodels (40 MW battery storage)

Newton Of Pitfodels is a 40 MW battery storage project in Aberdeen City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 March 2025, not yet built; the record was last updated on 23 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
23 April 2025record last updated
Aberdeen Citycouncil area

Planning timeline

DateStage
20 May 2024Application submitted
19 September 2024Refused by the planning authority
13 December 2024Appeal lodged
28 March 2025Planning permission granted
28 March 2025Appeal allowed
28 March 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
23 April 2025
Operator or applicant
Flexion Energy Uk Storage
Planning authority
Aberdeen City
Planning application reference
240614/DPP
Appeal reference
A240012
Address (REPD)
Newton Of Pitfodels
Council area (by location)
Aberdeen City
Time to decision
45 weeks
Name in REPD
Newton Of Pitfodels - Battery Storage
REPD reference
13606

Who decides

ApplicationsAberdeen CityUK
Decided applications (solar, wind, battery)2210,236
Refused2 (9%)19%
Solar refused0 of 1512%
Battery storage refused2 of 716%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
A981 Fraserburghbattery storage25approved, not built2.4
Aberdeen Hydrogen Hub Facilitysolar farm8abandoned3.4
Craigshaw Drive Battery Storage Facility & Electric Vehicle Charging Hubbattery storage20approved, not built4.9
Bankhead Recycling Solar Array, Battery Storage & Hydrogenbattery storage5approved, not built5.3
Persley BESSbattery storage70approved, not built5.7
Persley Croftbattery storage49.9approved, not built6.0
Rigifa Cove Roadbattery storage49.9approved, not built6.1
Farburn Placebattery storage30under construction8.2
Lower Bodachrasolar farm72approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1287, -2.1732).