Solar, wind and battery projects near Aberdeen (AB15)
34 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB15 (Aberdeen City): 1 is waiting for a planning decision, 27 approved but not yet running, 2 operational. The largest live scheme is Lower Bodachra (72 MW solar farm, approved on 24 June 2025, not yet built), 7.6 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Kincardine Offshore Windfarm (49.5 MW, operational), 23.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of AB15
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Newton Of Pitfodelsbattery storage | battery storage | 40 | approved, not builtupdated Apr 2025 | May 2024 | granted Mar 2025 | Apr 2025 | Aberdeen City | 1.0 |
| A981 Fraserburghbattery storage | battery storage | 25 | approved, not built may be out of dateupdated Feb 2022 | Dec 2021 | granted Feb 2022 | Feb 2022 | Aberdeen City | 1.8 |
| St Johns Terracesolar farm | solar farm | 1.3 | no application requiredupdated Sep 2021 | — | — | Sep 2021 | Aberdeen City | 2.0 |
| Airyhall Distribution Service Reservoir, St Johns Terracerooftop solar | rooftop solar | 1.1 | approved, not builtupdated Oct 2023 | Mar 2023 | granted Sep 2023 | Oct 2023 | Aberdeen City | 2.0 |
| Aberdeen Hydrogen Hub Facilitysolar farm | solar farm | 8 | abandonedupdated Jun 2026 | Mar 2023 | granted Jun 2023 | Jun 2026 | Aberdeen City | 2.4 |
| Drumforskiesolar farm | solar farm | 2.5 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Aberdeen City | 4.6 |
| Persley BESSbattery storage | battery storage | 70 | approved, not builtupdated Jul 2025 | Apr 2024 | granted Jun 2025 | Jul 2025 | Aberdeen City | 4.7 |
| Persley Croftbattery storage | battery storage | 49.9 | approved, not builtupdated Dec 2025 | Sep 2023 | granted Aug 2024 | Dec 2025 | Aberdeen City | 5.0 |
| Craigshaw Drive Battery Storage Facility & Electric Vehicle Charging Hubbattery storage | battery storage | 20 | approved, not builtupdated Oct 2024 | Mar 2024 | granted Oct 2024 | Oct 2024 | Aberdeen City | 5.0 |
| Bankhead Recycling Solar Array, Battery Storage & Hydrogenbattery storage | battery storage | 5 | approved, not builtupdated May 2023 | Aug 2022 | granted Apr 2023 | May 2023 | Aberdeenshire | 6.1 |
| Bankhead Recycling Solar Array, Battery Storage & Hydrogensolar farm | solar farm | 3 | approved, not builtupdated May 2023 | Aug 2022 | granted Apr 2023 | May 2023 | Aberdeenshire | 6.3 |
| Nigg Waste Water Plant, Coast Road Solar PV Arraysrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Sep 2023 | Oct 2023 | Aberdeen City | 6.5 |
| Rigifa Cove Roadbattery storage | battery storage | 49.9 | approved, not builtupdated Jun 2026 | Oct 2023 | granted Nov 2024 | Jun 2026 | Aberdeen City | 6.7 |
| Farburn Placebattery storage | battery storage | 30 | under constructionupdated Oct 2025 | May 2021 | granted Sep 2021 | Oct 2025 | Aberdeen City | 7.3 |
| Lower Bodachrasolar farm | solar farm | 72 | approved, not builtupdated Feb 2026 | Sep 2024 | granted Jun 2025 | Feb 2026 | Aberdeen City | 7.6 |
| Aryburn Farm, Dycebattery storage | battery storage | 49.9 | refusedupdated Dec 2025 | Oct 2024 | refused Nov 2025 | Dec 2025 | Aberdeen City | 8.2 |
| Lower Bodachrabattery storage | battery storage | 45 | approved, not builtupdated Feb 2026 | Sep 2024 | granted Jun 2025 | Feb 2026 | Aberdeen City | 8.5 |
| Dyce Energy Storage, Raiths Industrial Estate Battery Facilitybattery storage | battery storage | 50 | operationalupdated Sep 2024 | Jan 2022 | granted May 2022 | Sep 2024 | Aberdeen City | 8.7 |
Smaller schemes under 1 MW, mostly rooftop solar (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ithaca Energy, Hill Of Rubislawrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | Aberdeen City | 1.2 |
| Pitfodels House, North Deeside Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Aberdeen City | 1.7 |
| David Lloyd, Garthdee Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2024 | Jan 2024 | granted May 2024 | Jun 2024 | Aberdeen City | 3.3 |
| Health And Fitness Club, Garthdee Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Aberdeen City | 3.3 |
| North East Scotland Collegerooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Feb 2022 | Jan 2022 | granted Mar 2022 | Feb 2022 | Aberdeen City | 4.5 |
| First Aberdeen, King Streetrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Apr 2023 | Mar 2023 | granted Apr 2023 | Apr 2023 | Aberdeen City | 5.0 |
| Joseph Robertson Limited, Sinclair Roadrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Aberdeen City | 5.1 |
| North East Scotland Collegerooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Feb 2022 | Jan 2022 | granted Mar 2022 | Feb 2022 | Aberdeen City | 6.1 |
| Peterseat Driverooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Aberdeen City | 6.3 |
| Enterprise Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | Aberdeenshire | 7.1 |
| Kings Church, Kings Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Aberdeen City | 7.3 |
| Badentoy Drive, Portlethenrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Jan 2022 | Jan 2022 | granted Mar 2022 | Jan 2022 | Aberdeenshire | 7.3 |
| One Subsea, Badentoy Avenuerooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Dec 2022 | Jan 2023 | Aberdeenshire | 7.6 |
| Iron Mountain Howe Moss Driverooftop solar | rooftop solar | 0.3 | operationalupdated Mar 2023 | Jun 2019 | granted Sep 2019 | Mar 2023 | Aberdeen City | 7.7 |
| Schoeller Bleckmann Darron, Kirkhill Industrial Estaterooftop solar | rooftop solar | 0.3 | application withdrawn | May 2026 | — | — | Aberdeen City | 8.4 |
| Siemens, Kirkton Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Nov 2023 | granted Feb 2024 | Mar 2024 | Aberdeen City | 8.5 |
Distance from the average position of the AB15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 1 | 2 | 0 | 0 | 77.5 |
| Rooftop solar | 18 | 0 | 16 | 1 | 0 | 5.8 |
| Battery storage | 11 | 0 | 9 | 1 | 1 | 335 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Kincardine Offshore Windfarm | 49.5 | operationalupdated Mar 2022 | 23.7 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Aberdeen City decides solar, wind and battery applications
| Applications | Aberdeen City | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 22 | 10,236 |
| Refused | 2 (9%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 13.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB15, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.