Dyce Energy Storage, Raiths Industrial Estate Battery Facility (50 MW)

Dyce Energy Storage, Raiths Industrial Estate Battery Facility is a 50 MW battery storage project in Aberdeen City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2023; the record was last updated on 9 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
operationalstatus in REPD
9 September 2024record last updated
Aberdeen Citycouncil area

Planning timeline

DateStage
31 January 2022Application submitted
30 May 2022Planning permission granted
1 September 2023Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
operational
Record last updated
9 September 2024
Operator or applicant
Intelligent Land Investments Group
Planning authority
Aberdeen City
Planning application reference
220026/DPP
Address (REPD)
Raiths Industrial Estate, By Kirkton Drive, Pitmedden Road, Dyce, Aberdeen
Council area (by location)
Aberdeen City
Time to decision
17 weeks
Name in REPD
Dyce Energy Storage, Raiths Industrial Estate - Battery Facility
REPD reference
9388

Who decides

ApplicationsAberdeen CityUK
Decided applications (solar, wind, battery)2210,236
Refused2 (9%)19%
Solar refused0 of 1512%
Battery storage refused2 of 716%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Farburn Placebattery storage30under construction1.5
Aryburn Farm, Dycebattery storage49.9refused1.9
Lower Bodachrasolar farm72approved, not built3.0
Persley Croftbattery storage49.9approved, not built4.9
Persley BESSbattery storage70approved, not built4.9
Middleton Of Potterton Farmbattery storage49.9approved, not built5.8
Aberdeen Hydrogen Hub Facilitysolar farm8abandoned7.3
Broomhill BESSbattery storage49approved, not built8.3
Kintore Battery Energy Storage Projectbattery storage300approved, not built8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2139, -2.2031).