Broomhill BESS (49 MW)

Broomhill BESS is a 49 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 July 2022, not yet built; the record was last updated on 17 June 2026. REPD also records that the planning permission expired on 1 July 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWbattery storage
approved, not builtmay be out of datestatus in REPD
17 June 2026record last updated
Aberdeenshirecouncil area

REPD also records that the planning permission expired on 1 July 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
17 February 2022Application submitted
1 July 2022Planning permission granted
1 July 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49 MW
Status (REPD)
approved, not built
Record last updated
17 June 2026
Operator or applicant
Gigabox Energy Storage Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2022/0249
Address (REPD)
Midmill Kintore Aberdeenshire
Council area (by location)
Aberdeenshire
Time to decision
19 weeks
Name in REPD
Broomhill BESS - Battery Energy Storage
REPD reference
10701

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kintore Battery Energy Storage Projectbattery storage300approved, not built0.3
Womblehill Farm, Kintorebattery storage200application submitted1.4
Fordtown Energy Storagebattery storage49.9approved, not built1.6
Kintoresolar farm50application submitted1.8
Kintore Substation, Leylodgebattery storage49.9approved, not built2.1
South Leylodge Farmhouse, Kintorebattery storage49.9approved, not built2.9
Dyce Energy Storage, Raiths Industrial Estate Battery Facilitybattery storage50operational8.3
Farburn Placebattery storage30under construction9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2156, -2.3414).