Solar, wind and battery projects near Westhill (AB32)
21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB32 (Aberdeenshire): 3 are waiting for a planning decision, 15 approved but not yet running, 2 operational. The largest live scheme is Kintore Battery Energy Storage Project (300 MW battery storage, approved on 7 May 2025, not yet built), 7.2 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Kincardine Offshore Windfarm (49.5 MW, operational), 32.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of AB32
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Cullerlie Solar Farmsolar farm | solar farm | 13 | approved, not builtupdated Nov 2021 | Feb 2021 | granted Nov 2021 | Nov 2021 | Aberdeenshire | 4.9 |
| Kintoresolar farm | solar farm | 50 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 | Aberdeenshire | 5.9 |
| Kintorebattery storage | battery storage | 40 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 | Aberdeenshire | 5.9 |
| Broomhill BESSbattery storage | battery storage | 49 | approved, not built may be out of dateupdated Jun 2026 | Feb 2022 | granted Jul 2022 | Jun 2026 | Aberdeenshire | 6.9 |
| Kintore Battery Energy Storage Projectbattery storage | battery storage | 300 | approved, not builtupdated Jul 2025 | Feb 2021 | granted May 2025 | Jul 2025 | Aberdeenshire | 7.2 |
| Womblehill Farm, Kintorebattery storage | battery storage | 200 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 | Aberdeenshire | 7.5 |
| South Leylodge Farmhouse, Kintorebattery storage | battery storage | 49.9 | approved, not builtupdated May 2024 | Sep 2022 | granted Apr 2023 | May 2024 | Aberdeenshire | 7.8 |
| Kintore Substation, Leylodgebattery storage | battery storage | 49.9 | approved, not builtupdated Oct 2024 | Dec 2023 | granted Sep 2024 | Oct 2024 | Aberdeenshire | 7.9 |
| Fordtown Energy Storagebattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated May 2022 | Sep 2020 | granted Feb 2021 | May 2022 | Aberdeenshire | 7.9 |
| Newton Of Pitfodelsbattery storage | battery storage | 40 | approved, not builtupdated Apr 2025 | May 2024 | granted Mar 2025 | Apr 2025 | Aberdeen City | 9.2 |
| Farburn Placebattery storage | battery storage | 30 | under constructionupdated Oct 2025 | May 2021 | granted Sep 2021 | Oct 2025 | Aberdeen City | 9.3 |
| Dyce Energy Storage, Raiths Industrial Estate Battery Facilitybattery storage | battery storage | 50 | operationalupdated Sep 2024 | Jan 2022 | granted May 2022 | Sep 2024 | Aberdeen City | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Enterprise Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | Aberdeenshire | 2.1 |
| Archer House, Main Road, Blackburnrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Jul 2022 | Jul 2022 | granted Aug 2022 | Jul 2022 | Aberdeenshire | 5.5 |
| Ellismosssolar farm | solar farm | 0.4 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Aberdeenshire | 5.5 |
| Forest Farm Dairy, Glasgoforestrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Dec 2022 | Nov 2022 | granted Dec 2022 | Dec 2022 | Aberdeenshire | 5.6 |
| Oeg offshore, Tofthills Wayrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Aberdeenshire | 7.6 |
| Iron Mountain Howe Moss Driverooftop solar | rooftop solar | 0.3 | operationalupdated Mar 2023 | Jun 2019 | granted Sep 2019 | Mar 2023 | Aberdeen City | 7.8 |
| Donald Russell, Carnie Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Jan 2024 | Feb 2024 | Aberdeenshire | 8.2 |
| Schoeller Bleckmann Darron, Kirkhill Industrial Estaterooftop solar | rooftop solar | 0.3 | application withdrawn | May 2026 | — | — | Aberdeen City | 8.6 |
| Siemens, Kirkton Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Nov 2023 | granted Feb 2024 | Mar 2024 | Aberdeen City | 9.5 |
Distance from the average position of the AB32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 1 | 2 | 0 | 0 | 63.4 |
| Rooftop solar | 8 | 0 | 6 | 1 | 0 | 1.9 |
| Battery storage | 10 | 2 | 7 | 1 | 0 | 809 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Kincardine Offshore Windfarm | 49.5 | operationalupdated Mar 2022 | 32.0 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Aberdeenshire decides solar, wind and battery applications
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB32, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.