Womblehill Farm, Kintore (200 MW battery storage)

Womblehill Farm, Kintore is a 200 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 27 June 2025, no decision recorded; the record was last updated on 6 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
application submittedstatus in REPD
6 October 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
27 June 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
application submitted
Record last updated
6 October 2025
Operator or applicant
RE Projects Development (REPD) / Field
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005233
Address (REPD)
Womblehill, Kintore
Council area (by location)
Aberdeenshire
Name in REPD
Womblehill Farm, Kintore - Battery Energy Storage System
REPD reference
17325

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Fordtown Energy Storagebattery storage49.9approved, not built0.4
Kintore Substation, Leylodgebattery storage49.9approved, not built0.7
Kintore Battery Energy Storage Projectbattery storage300approved, not built1.3
Broomhill BESSbattery storage49approved, not built1.4
South Leylodge Farmhouse, Kintorebattery storage49.9approved, not built1.7
Kintoresolar farm50application submitted1.7
Dyce Energy Storage, Raiths Industrial Estate Battery Facilitybattery storage50operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2179, -2.3639).