Cullerlie Solar Farm (13 MW)

Cullerlie Solar Farm is a 13 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 November 2021, not yet built; the record was last updated on 16 November 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13 MWsolar farm
approved, not builtstatus in REPD
16 November 2021record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
22 February 2021Application submitted
12 November 2021Planning permission granted
12 November 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
13 MW
Status (REPD)
approved, not built
Record last updated
16 November 2021
Operator or applicant
Elgin Energy ES Co Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2021/0378
Site area
18.9 ha
Address (REPD)
Lands South Of Cornhill Farm Echt Westhill
Council area (by location)
Aberdeenshire
Time to decision
38 weeks
Contracts for Difference
AR4
REPD reference
8842

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill of Fare Wind Farm & Battery Storagewind farm106application submitted8.0
Kintoresolar farm50application submitted9.4
Hill of Fare Wind Farmwind farm150abandoned9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1183, -2.3638).