Energy Projects Near You

Hill of Fare Wind Farm & Battery Storage (106 MW)

Hill of Fare Wind Farm & Battery Storage is a 106 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 6 November 2023, no decision recorded; the record was last updated on 24 November 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

106 MWwind farm
application submittedmay be out of datestatus in REPD
24 November 2023record last updated
Aberdeenshirecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
6 November 2023Application submitted

Project details

Technology
wind farm
Capacity
106 MW
Status (REPD)
application submitted
Record last updated
24 November 2023
Operator or applicant
RES Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004592
Turbines
16
Turbine height
200 m
Address (REPD)
Hill of Fare, Banchory
Council area (by location)
Aberdeenshire
Name in REPD
Hill of Fare - Hill of Fare Wind Farm & Battery Storage
REPD reference
12025

The scheme also includes 100 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill of Fare Wind Farmwind farm150abandoned1.5
Cullerlie Solar Farmsolar farm13approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1144, -2.4959).