Energy Projects Near You

Solar, wind and battery projects near Banchory (AB31)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB31 (Aberdeenshire): 3 are waiting for a planning decision. The largest live scheme is Hill of Fare Wind Farm & Battery Storage (106 MW wind farm, application submitted on 6 November 2023, no decision recorded; REPD status may be out of date), 4.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
3awaiting a decision
0approved, not running
0operational

Projects within 10 km of AB31

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hill of Fare Wind Farmwind farmwind farm150abandonedupdated Sep 2018——Sep 2018Aberdeenshire4.4
Hill of Fare Wind Farm & Battery Storagewind farmwind farm106application submitted may be out of dateupdated Nov 2023Nov 2023—Nov 2023Aberdeenshire4.9
Hill of Fare Wind Farm & Battery Storagebattery storagebattery storage100application submitted may be out of dateupdated Nov 2023Nov 2023—Nov 2023Aberdeenshire4.9
Auchorie Farm, Midmarwind farmwind farm1.6application submittedupdated Mar 2026Mar 2026—Mar 2026Aberdeenshire7.9

Distance from the average position of the AB31 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm32000107
Battery storage11000100

MW in pipeline: pending, approved and under-construction capacity.

How Aberdeenshire decides solar, wind and battery applications

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

All projects in Aberdeenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB31, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.