Energy Projects Near You

Solar, wind and battery projects near Peterculter (AB14)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB14 (Aberdeen City): 1 is waiting for a planning decision, 13 approved but not yet running, 1 operational. The largest live scheme is Newton Of Pitfodels (40 MW battery storage, approved on 28 March 2025, not yet built), 6.7 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Kincardine Offshore Windfarm (49.5 MW, operational), 26.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
1awaiting a decision
13approved, not running
1operational

Projects within 10 km of AB14

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cullerlie Solar Farmsolar farmsolar farm13approved, not builtupdated Nov 2021Feb 2021granted Nov 2021Nov 2021Aberdeenshire5.9
Newton Of Pitfodelsbattery storagebattery storage40approved, not builtupdated Apr 2025May 2024granted Mar 2025Apr 2025Aberdeen City6.7
St Johns Terracesolar farmsolar farm1.3no application requiredupdated Sep 2021——Sep 2021Aberdeen City8.4
Airyhall Distribution Service Reservoir, St Johns Terracerooftop solarrooftop solar1.1approved, not builtupdated Oct 2023Mar 2023granted Sep 2023Oct 2023Aberdeen City8.4
Bankhead Recycling Solar Array, Battery Storage & Hydrogensolar farmsolar farm3approved, not builtupdated May 2023Aug 2022granted Apr 2023May 2023Aberdeenshire8.6
Bankhead Recycling Solar Array, Battery Storage & Hydrogenbattery storagebattery storage5approved, not builtupdated May 2023Aug 2022granted Apr 2023May 2023Aberdeenshire8.9
Meikle Carewewind farmwind farm10operationalupdated Jun 2014Nov 2006granted May 2010Jun 2014Aberdeenshire9.1
A981 Fraserburghbattery storagebattery storage25approved, not built may be out of dateupdated Feb 2022Dec 2021granted Feb 2022Feb 2022Aberdeen City9.1
Drumforskiesolar farmsolar farm2.5application submittedupdated Jan 2026Dec 2025—Jan 2026Aberdeen City9.4
Aberdeen Hydrogen Hub Facilitysolar farmsolar farm8abandonedupdated Jun 2026Mar 2023granted Jun 2023Jun 2026Aberdeen City9.7
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Enterprise Driverooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2022May 2022granted Jul 2022May 2022Aberdeenshire5.4
Pitfodels House, North Deeside Roadrooftop solarrooftop solar0.6approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Aberdeen City7.2
One Subsea, Badentoy Avenuerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Jan 2023Nov 2022granted Dec 2022Jan 2023Aberdeenshire7.8
Badentoy Drive, Portlethenrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Jan 2022Jan 2022granted Mar 2022Jan 2022Aberdeenshire7.8
Ithaca Energy, Hill Of Rubislawrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Sep 2022Aug 2022granted Sep 2022Sep 2022Aberdeen City8.6
David Lloyd, Garthdee Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2024Jan 2024granted May 2024Jun 2024Aberdeen City9.0
Health And Fitness Club, Garthdee Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Aberdeen City9.1

Distance from the average position of the AB14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5120018.5
Rooftop solar808003.4
Wind farm100100
Battery storage3030070

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Kincardine Offshore Windfarm49.5operationalupdated Mar 202226.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Aberdeen City decides solar, wind and battery applications

ApplicationsAberdeen CityUK
Decided applications (solar, wind, battery)2210,236
Refused2 (9%)19%
Solar refused0 of 1512%
Battery storage refused2 of 716%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Aberdeen City

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB14, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.