Kincardine offshore wind farm

Kincardine Offshore Windfarm is a 49.5 MW offshore wind farm with 6 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 October 2021; the record was last updated on 2 March 2022. Its REPD grid reference is 16 km from the nearest postcode on land (AB12 4NS, Aberdeenshire). As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWoffshore wind farm
operationalstatus in REPD
2 March 2022record last updated
16 km from land (Aberdeenshire)REPD location

Consent timeline

DateStage
16 June 2016Application submitted
7 March 2017Marine licence and Section 36 consent granted (Scottish Ministers)
1 October 2018Construction started
19 October 2021Operational

Project details

Technology
offshore wind farm
Capacity
49.5 MW
Turbines
6
Turbine height
176 m
Status (REPD)
operational
Record last updated
2 March 2022
Operator or applicant
Grupo Cobra
Consenting authority (REPD)
Marine Scotland
Application reference
APP/2016/1726
Nearest postcode on land
AB12 4NS (Aberdeenshire), 15.9 km from the REPD grid reference
Time to decision
38 weeks
REPD reference
6136

Who decides

As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Postcode districts within 40 km

Districtkm
Aberdeen (AB12)18.6
Aberdeen (AB11)20.6
Stonehaven (AB39)20.7
Aberdeen (AB10)21.4
Aberdeen (AB25)22.6
Aberdeen (AB24)23.3
Aberdeen (AB15)23.7
Aberdeen (AB16)24.9
Milltimber (AB13)25.1
Aberdeen (AB22)25.9
Peterculter (AB14)26.7
Aberdeen (AB23)27.2

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
European Offshore Wind Deployment Centre (EOWDC) (Aberdeen Bay - Demonstration site)96.8operational20.5

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (56.9973, -1.8738).