European Offshore Wind Deployment Centre (EOWDC) (Aberdeen Bay - Demonstration site) offshore wind farm

European Offshore Wind Deployment Centre (EOWDC) (Aberdeen Bay - Demonstration site) is a 96.8 MW offshore wind farm with 11 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 September 2018; the record was last updated on 30 April 2019. REPD gives a grid reference on the coast (AB11 5DP, Aberdeen City), not the position of the turbines, so the distance out to sea is not known from REPD. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

96.8 MWoffshore wind farm
operationalstatus in REPD
30 April 2019record last updated
on the coast (Aberdeen City)REPD location

Consent timeline

DateStage
31 August 2011Application submitted
26 March 2013Section 36 consent granted (Scottish Ministers)
7 April 2018Construction started
7 September 2018Operational

Project details

Technology
offshore wind farm
Capacity
96.8 MW
Turbines
11
Turbine capacity
8.8 MW
Status (REPD)
operational
Record last updated
30 April 2019
Operator or applicant
Vattenfall
Consenting authority (REPD)
Scottish Government (S36)
Application reference
not recorded
Nearest postcode on land
AB11 5DP (Aberdeen City), 0.2 km from the REPD grid reference
Time to decision
82 weeks
REPD reference
2505

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Kincardine Offshore Windfarm49.5operational20.5

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (57.1462, -2.0728), which is on the coast rather than at the turbines.