Kildrummy Windfarm (18.4 MW)

Kildrummy Windfarm is an 18.4 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 February 2013; the record was last updated on 26 June 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
operationalstatus in REPD
26 June 2014record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
19 December 2006Application submitted
24 September 2007Refused by the planning authority
6 August 2009Planning permission granted
6 August 2009Appeal allowed
14 February 2013Operational

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
operational
Record last updated
26 June 2014
Operator or applicant
Greencoat UK Wind/Bay Wa .r.e/ SunGift
Planning authority
Aberdeenshire
Planning application reference
APP/2006/4911
Appeal reference
P/PPA/110/712
Turbines
8
Address (REPD)
Clashnarae Hill, Kildrummy, Alford
Council area (by location)
Aberdeenshire
Time to decision
137 weeks
REPD reference
4114

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pressendyewind farm16.1refused on appeal1.1
Tibberchindy Wind Farmwind farm18refused6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2253, -2.7029).