Tibberchindy Wind Farm (18 MW)
Tibberchindy Wind Farm is an 18 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 4 February 2014; the record was last updated on 13 March 2014.
18 MWwind farm
refusedstatus in REPD
13 March 2014record last updated
Aberdeenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 15 October 2012 | Application submitted |
| 4 February 2014 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 18 MW
- Status (REPD)
- refused
- Record last updated
- 13 March 2014
- Operator or applicant
- Ventient (formerly Infinis)
- Planning authority
- Aberdeenshire
- Planning application reference
- APP/2012/3405
- Turbines
- 6
- Address (REPD)
- Coiliochbhar Hill, nr Tibberchindy Farmhouse 5km west of Alford, Aberdeenshire
- Council area (by location)
- Aberdeenshire
- Time to decision
- 68 weeks
- REPD reference
- 3872
Who decides
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Kildrummy Windfarm | wind farm | 18.4 | operational | 6.7 |
| Hill of Snowy Slack | wind farm | 22 | application withdrawn | 6.8 |
| Pressendye | wind farm | 16.1 | refused on appeal | 6.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2223, -2.8143).