Energy Projects Near You

Pressendye (16.1 MW wind farm)

Pressendye is a 16.1 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 12 November 2010; the record was last updated on 6 December 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.1 MWwind farm
refused on appealstatus in REPD
6 December 2010record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
5 February 2008Application submitted
12 November 2010Appeal refused
12 July 2016Refused by the planning authority

Project details

Technology
wind farm
Capacity
16.1 MW
Status (REPD)
refused on appeal
Record last updated
6 December 2010
Operator or applicant
West Coast Energy
Planning authority
Aberdeenshire
Planning application reference
APP/2008/0237
Appeal reference
PPA-110-2014
Turbines
7
Address (REPD)
Cushnie, Alford, Grampian. AB33 8AE
Council area (by location)
Aberdeenshire
Time to decision
440 weeks
REPD reference
2692

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kildrummy Windfarmwind farm18.4operational1.1
Tibberchindy Wind Farmwind farm18refused6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2352, -2.703).