Energy Projects Near You

Seagreen offshore wind farm

Seagreen is a 1,075 MW offshore wind farm with 114 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 October 2023; the record was last updated on 18 October 2023. Its REPD grid reference is 30 km from the nearest postcode on land (DD10 0AL, Aberdeenshire). As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,075 MWoffshore wind farm
operationalstatus in REPD
18 October 2023record last updated
30 km from land (Aberdeenshire)REPD location

Consent timeline

DateStage
23 October 2012Application submitted
16 May 2017Marine licence and Section 36 consent granted (Scottish Ministers)
1 May 2021Construction started
16 October 2023Operational

Project details

Technology
offshore wind farm
Capacity
1,075 MW
Turbines
114
Turbine capacity
10 MW (SSE; REPD: 9.2 MW)
Status (REPD)
operational
Record last updated
18 October 2023
Operator or applicant
SSE / Seagreen Wind Energy Ltd
Consenting authority (REPD)
Marine Scotland
Application reference
not recorded
Nearest postcode on land
DD10 0AL (Aberdeenshire), 30.3 km from the REPD grid reference
Time to decision
238 weeks
Contracts for Difference
AR3
REPD reference
2540

Who decides

As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Postcode districts within 40 km

Districtkm
Montrose (DD10)33.0

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Seagreen Phase 1A540approved, not built<0.1
Inch Cape1,080under construction22.5

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (56.6355, -1.9266).

Seagreen is the largest operational offshore wind farm in Scottish waters and the third largest by capacity among those operational in the UK, both places per the REPD extract for July 2026. It has 114 turbines of 10 MW each (9.2 in the REPD), a capacity of 1,075 MW; the site sits 30 km from the nearest postcode in Aberdeenshire, with DD10 (Montrose) 33.0 km away.

SSE and Seagreen Wind Energy Ltd submitted the application on 23 October 2012. The register dates the marine licence and the Section 36 consent (Marine Scotland as the authority) to 16 May 2017, more than four times the median of 56.6 weeks. On that same day the Court of Session reinstated the consent granted by Scottish Ministers, which RSPB had challenged; Inch Cape shares that date, under construction 22.5 km away at 1,080 MW. The Contract for Difference came in round AR3, construction ran from 1 May 2021, and the wind farm has been operational since 16 October 2023.

Seagreen Phase 1A

The register lists Seagreen Phase 1A at the same location, at 540 MW: approved, not built. The record was last updated on 18 October 2023.