Energy Projects Near You

Cameron Reservoir (5 MW solar farm)

Cameron Reservoir is a 5 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 27 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
27 September 2018record last updated
Fifecouncil area

Planning timeline

DateStage
20 April 2015Application submitted
13 October 2015Planning permission granted
13 October 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
27 September 2018
Operator or applicant
Green Power Consultants
Planning authority
Fife
Planning application reference
15/00538/FULL
Site area
10.0 ha
Address (REPD)
Cameron Reservoir, Cameron Drive, Kirkcaldy
Council area (by location)
Fife
Time to decision
25 weeks
REPD reference
5338

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lingo Wind Farmwind farm12.5refused on appeal3.7
Gathercauldwind farm15.6refused5.2
Kenly Wind Farmwind farm12.3approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.283, -2.8465).