Earlseat (18.4 MW wind farm)

Earlseat is an 18.4 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 July 2014; the record was last updated on 20 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
operationalstatus in REPD
20 August 2014record last updated
Fifecouncil area

Planning timeline

DateStage
17 September 2010Application submitted
2 March 2012Planning permission granted
30 October 2013Construction started
30 July 2014Operational

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
operational
Record last updated
20 August 2014
Operator or applicant
The Renewables Infrastructure Group (TRIG)
Planning authority
Fife
Planning application reference
10/03539/EIA
Turbines
8
Address (REPD)
Earlseat Farm Standing Stane Road Kirkcaldy Fife KY1 4TH
Council area (by location)
Fife
Time to decision
76 weeks
REPD reference
4363

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wemyss Estate - Randolph Solar Farm & Battery Energy Storagesolar farm50approved, not built2.7
Duniface Gas Peaking Plantbattery storage49.9approved, not built3.5
West Strathore Solar Limitedsolar farm5operational4.4
Land North of Balbeggie Avenuesolar farm12approved, not built4.7
Land North of Thornton Roadbattery storage19.9approved, not built4.9
Middle Balbeggiesolar farm5operational5.0
Wester Balbeggie Farm, Balbeggie Avenuebattery storage49approved, not built5.4
Middle Balbeggie Wind Turbineswind farm6.4operational5.6
Clattowind farm30refused6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1737, -3.0813).