Energy Projects Near You

Wester Balbeggie Farm, Balbeggie Avenue (49 MW battery storage)

Wester Balbeggie Farm, Balbeggie Avenue is a 49 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 August 2023, not yet built; the record was last updated on 30 August 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWbattery storage
approved, not builtstatus in REPD
30 August 2023record last updated
Fifecouncil area

Planning timeline

DateStage
8 May 2023Application submitted
17 August 2023Planning permission granted
17 August 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49 MW
Status (REPD)
approved, not built
Record last updated
30 August 2023
Operator or applicant
Relay Balbeggie Limited
Planning authority
Fife
Planning application reference
23/00701/FULL
Address (REPD)
300M East Of Wester Balbeggie Cottages Wester Balbeggie Farm Balbeggie Avenue Balbeggie Thornton
Council area (by location)
Fife
Time to decision
14 weeks
Name in REPD
Wester Balbeggie Farm, Balbeggie Avenue - Battery Storage
REPD reference
12350

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middle Balbeggie Wind Turbineswind farm6.4operational0.4
Land North of Balbeggie Avenuesolar farm12approved, not built0.7
Middle Balbeggiesolar farm5operational0.8
Land North of Thornton Roadbattery storage19.9approved, not built1.2
West Strathore Solar Limitedsolar farm5operational1.5
Wemyss Estate - Randolph Solar Farm & Battery Energy Storagesolar farm50approved, not built2.7
Earlseatwind farm18.4operational5.4
Strathruddie, Kinglassie Solar farmsolar farm25approved, not built6.3
Roaring Hill, Whinnyknowebattery storage60application submitted6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1518, -3.1584).