Energy Projects Near You

Middle Balbeggie Wind Turbines (6.4 MW)

Middle Balbeggie Wind Turbines is a 6.4 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 November 2016; the record was last updated on 4 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.4 MWwind farm
operationalstatus in REPD
4 May 2017record last updated
Fifecouncil area

Planning timeline

DateStage
28 September 2012Application submitted
17 June 2013Refused by the planning authority
29 January 2014Planning permission granted
29 January 2014Appeal allowed
15 June 2015Construction started
20 November 2016Operational

Project details

Technology
wind farm
Capacity
6.4 MW
Status (REPD)
operational
Record last updated
4 May 2017
Operator or applicant
Capital Dynamics
Planning authority
Fife
Planning application reference
12/04094/EIA
Appeal reference
13/00035/REF
Turbines
2
Address (REPD)
Land Surrounding Middle Balbeggie Balbeggie Avenue Balbeggie Thornton Fife
Council area (by location)
Fife
Time to decision
70 weeks
REPD reference
4094

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wester Balbeggie Farm, Balbeggie Avenuebattery storage49approved, not built0.4
Land North of Balbeggie Avenuesolar farm12approved, not built0.9
Middle Balbeggiesolar farm5operational1.3
West Strathore Solar Limitedsolar farm5operational1.5
Land North of Thornton Roadbattery storage19.9approved, not built1.6
Wemyss Estate - Randolph Solar Farm & Battery Energy Storagesolar farm50approved, not built2.9
Earlseatwind farm18.4operational5.6
Strathruddie, Kinglassie Solar farmsolar farm25approved, not built5.9
Roaring Hill, Whinnyknowebattery storage60application submitted6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1537, -3.1645).