Roaring Hill, Whinnyknowe (60 MW battery storage)

Roaring Hill, Whinnyknowe is a 60 MW battery storage project in Fife, Scotland. Its status: consented by Scottish Ministers on 27 October 2026, not yet built (Scottish Government Energy Consents Unit). The Renewable Energy Planning Database (July 2026 extract) still records: application submitted on 23 July 2025, no decision recorded; the record was last updated on 14 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWbattery storage
approved, not builtstatus (Scottish Government Energy Consents Unit; status in REPD: application submitted)
14 October 2025record last updated
Fifecouncil area

Planning timeline

DateStage
23 July 2025Application submitted
27 October 2026Consent granted (Scottish Ministers)

Status source: Scottish Government Energy Consents Unit. The Renewable Energy Planning Database (July 2026 extract) still shows this project as “application submitted”.

Project details

Technology
battery storage (stand-alone storage)
Capacity
60 MW
Status
approved, not built (Scottish Government Energy Consents Unit; REPD: application submitted)
Record last updated
14 October 2025
Operator or applicant
ELM Power Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005104
Address (REPD)
Roaring Hill, Whinnyknowe, Leslie, Glenrothes
Council area (by location)
Fife
Name in REPD
Roaring Hill, Whinnyknowe - Battery Energy Storage System
REPD reference
16676

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Balsillie Avenue - Roaring Hill Energy Storage Facilitybattery storage19.9under construction0.3
Ballingall Farm, Lesliebattery storage43approved, not built0.8
Strathruddie, Kinglassie Solar farmsolar farm25approved, not built5.7
West Strathore Solar Limitedsolar farm5operational5.8
Westfield Solar Farm & Batterysolar farm30approved, not built5.9
Middle Balbeggie Wind Turbineswind farm6.4operational6.4
Land North of Balbeggie Avenuesolar farm12approved, not built6.5
Wester Balbeggie Farm, Balbeggie Avenuebattery storage49approved, not built6.8
Wemyss Estate - Randolph Solar Farm & Battery Energy Storagesolar farm50approved, not built7.2

Status and events credited to a named source are from that source; other dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2062, -3.207).