West Strathore Solar Limited (5 MW)

West Strathore Solar Limited is a 5 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2017; the record was last updated on 17 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
17 July 2017record last updated
Fifecouncil area

Planning timeline

DateStage
23 July 2015Application submitted
26 November 2015Planning permission granted
1 November 2016Construction started
30 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
17 July 2017
Operator or applicant
West Strathore Solar
Planning authority
Fife
Planning application reference
15/02351/FULL
Site area
7.3 ha
Address (REPD)
West Strathore House, Strathore Road, Thornton, Kirkcaldy, Fife
Council area (by location)
Fife
Time to decision
18 weeks
REPD reference
5384

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land North of Balbeggie Avenuesolar farm12approved, not built1.0
Middle Balbeggie Wind Turbineswind farm6.4operational1.5
Wester Balbeggie Farm, Balbeggie Avenuebattery storage49approved, not built1.5
Wemyss Estate - Randolph Solar Farm & Battery Energy Storagesolar farm50approved, not built1.9
Middle Balbeggiesolar farm5operational1.9
Land North of Thornton Roadbattery storage19.9approved, not built2.1
Earlseatwind farm18.4operational4.4
Balsillie Avenue - Roaring Hill Energy Storage Facilitybattery storage19.9under construction5.7
Roaring Hill, Whinnyknowebattery storage60application submitted5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1648, -3.151).