Middle Balbeggie (5 MW solar farm)
Middle Balbeggie is a 5 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 January 2017; the record was last updated on 4 April 2018.
5 MWsolar farm
operationalstatus in REPD
4 April 2018record last updated
Fifecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 September 2015 | Application submitted |
| 17 December 2015 | Planning permission granted |
| 17 October 2016 | Construction started |
| 27 January 2017 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- operational
- Record last updated
- 4 April 2018
- Operator or applicant
- Lightsource Renewable Energy
- Planning authority
- Fife
- Planning application reference
- 15/02687/FULL
- Site area
- 9.8 ha
- Address (REPD)
- Ld To N Of Redhouse Grid Subst, Thornton Road, Kirkcaldy
- Council area (by location)
- Fife
- Time to decision
- 13 weeks
- REPD reference
- 5797
Who decides
| Applications | Fife | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 17 (19%) | 19% |
| Solar refused | 0 of 36 | 12% |
| Onshore wind refused | 16 of 30 | 45% |
| Battery storage refused | 1 of 25 | 16% |
| Median time from submission to decision | 24.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Land North of Thornton Road | battery storage | 19.9 | approved, not built | 0.3 |
| Wester Balbeggie Farm, Balbeggie Avenue | battery storage | 49 | approved, not built | 0.8 |
| Land North of Balbeggie Avenue | solar farm | 12 | approved, not built | 1.0 |
| Middle Balbeggie Wind Turbines | wind farm | 6.4 | operational | 1.3 |
| West Strathore Solar Limited | solar farm | 5 | operational | 1.9 |
| Wemyss Estate - Randolph Solar Farm & Battery Energy Storage | solar farm | 50 | approved, not built | 2.3 |
| Earlseat | wind farm | 18.4 | operational | 5.0 |
| Strathruddie, Kinglassie Solar farm | solar farm | 25 | approved, not built | 7.1 |
| Little Raith Farm - extension | wind farm | 18 | refused on appeal | 7.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1479, -3.1467).