Energy Projects Near You

Balsillie Avenue - Roaring Hill Energy Storage Facility (19.9 MW)

Balsillie Avenue - Roaring Hill Energy Storage Facility is a 19.9 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 12 September 2022; the record was last updated on 15 September 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.9 MWbattery storage
under constructionstatus in REPD
15 September 2022record last updated
Fifecouncil area

Planning timeline

DateStage
25 May 2021Application submitted
3 September 2021Planning permission granted
12 September 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
19.9 MW
Status (REPD)
under construction
Record last updated
15 September 2022
Operator or applicant
Tag Energy UK
Planning authority
Fife
Planning application reference
21/01438/FULL
Address (REPD)
E/O Balsillie Avenue, The S/O The Limekilns, Glenrothes
Council area (by location)
Fife
Time to decision
14 weeks
REPD reference
9224

Earlier applications for this site

ApplicationMWSubmittedOutcome
Roaring Hill (Resubmission) 17/03318/FULL3017 October 2017replaced by a revised application

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Roaring Hill, Whinnyknowebattery storage60application submitted0.3
Ballingall Farm, Lesliebattery storage43approved, not built0.8
West Strathore Solar Limitedsolar farm5operational5.7
Strathruddie, Kinglassie Solar farmsolar farm25approved, not built5.9
Westfield Solar Farm & Batterysolar farm30approved, not built6.2
Middle Balbeggie Wind Turbineswind farm6.4operational6.4
Land North of Balbeggie Avenuesolar farm12approved, not built6.6
Wester Balbeggie Farm, Balbeggie Avenuebattery storage49approved, not built6.8
Wemyss Estate - Randolph Solar Farm & Battery Energy Storagesolar farm50approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2075, -3.2033).