Energy Projects Near You

Ballingall Farm, Leslie (43 MW battery storage)

Ballingall Farm, Leslie is a 43 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 September 2023, not yet built; the record was last updated on 18 March 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43 MWbattery storage
approved, not builtstatus in REPD
18 March 2022record last updated
Fifecouncil area

Planning timeline

DateStage
12 May 2023Application submitted
14 September 2023Planning permission granted
14 September 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
43 MW
Status (REPD)
approved, not built
Record last updated
18 March 2022
Operator or applicant
EcoDev Group Limited
Planning authority
Fife
Planning application reference
23/00971/FULL
Address (REPD)
Ballingall Farm, Leslie, Glenrothes
Council area (by location)
Fife
Time to decision
18 weeks
Name in REPD
Ballingall Farm, Leslie - Battery Energy Storage System
REPD reference
10825

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Balsillie Avenue - Roaring Hill Energy Storage Facilitybattery storage19.9under construction0.8
Roaring Hill, Whinnyknowebattery storage60application submitted0.8
Westfield Solar Farm & Batterysolar farm30approved, not built6.1
Strathruddie, Kinglassie Solar farmsolar farm25approved, not built6.2
West Strathore Solar Limitedsolar farm5operational6.5
Middle Balbeggie Wind Turbineswind farm6.4operational7.2
Land North of Balbeggie Avenuesolar farm12approved, not built7.4
Wester Balbeggie Farm, Balbeggie Avenuebattery storage49approved, not built7.6
Former Fife Power Stationbattery storage100application submitted7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2132, -3.2115).