North Calliachar Wind Farm (21 MW)
North Calliachar Wind Farm is a 21 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 28 March 2019.
21 MWwind farm
abandonedstatus in REPD
28 March 2019record last updated
Perth and Kinrosscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 April 2013 | Application submitted |
| 29 May 2014 | Refused by the planning authority |
| 8 August 2014 | Appeal lodged |
| 30 March 2015 | Planning permission granted |
| 30 March 2015 | Appeal allowed |
| 30 March 2018 | Permission expired |
Project details
- Technology
- wind farm
- Capacity
- 21 MW
- Status (REPD)
- abandoned
- Record last updated
- 28 March 2019
- Operator or applicant
- I & H Brown NC Ltd
- Planning authority
- Perth and Kinross
- Planning application reference
- 13/00653/FLM
- Appeal reference
- PPA-340-2087
- Turbines
- 7
- Address (REPD)
- Land 2000 Metres North Of Calliachar Wind Farm, Amulree
- Council area (by location)
- Perth and Kinross
- Time to decision
- 102 weeks
- REPD reference
- 4464
Who decides
| Applications | Perth and Kinross | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 73 | 10,236 |
| Refused | 32 (44%) | 19% |
| Solar refused | 6 of 24 | 12% |
| Onshore wind refused | 23 of 31 | 45% |
| Battery storage refused | 3 of 18 | 16% |
| Median time from submission to decision | 28.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Crossburns Wind Farm | wind farm | 75 | refused on appeal | 2.9 |
| Wind Farm at Meall Dearg Wind Farm | wind farm | 147 | application submitted | 4.2 |
| Calliachar | wind farm | 32.2 | operational | 5.8 |
| Griffin Wind farm | wind farm | 156 | operational | 8.1 |
| Creag A Bhaird | wind farm | 29.9 | refused on appeal | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5762, -3.8651).