Energy Projects Near You

Solar, wind and battery projects near Aberfeldy (PH15)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH15 (Perth and Kinross): 1 operational. The largest scheme is Crossburns Wind Farm (75 MW wind farm, refused on appeal on 6 October 2017), 3.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of PH15

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Crossburns Wind Farmwind farmwind farm75refused on appealupdated Oct 2017Oct 2014refused Oct 2017Oct 2017Perth and Kinross3.2
Calliacharwind farmwind farm32.2operationalupdated Dec 2013Feb 2004granted Sep 2007Dec 2013Perth and Kinross4.5
North Calliachar Wind Farmwind farmwind farm21abandonedupdated Mar 2019Apr 2013granted Mar 2015Mar 2019Perth and Kinross6.0

Distance from the average position of the PH15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm300110

MW in pipeline: pending, approved and under-construction capacity.

How Perth and Kinross decides solar, wind and battery applications

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in Perth and Kinross

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.