Energy Projects Near You

Solar, wind and battery projects near Ballinluig (PH9)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of PH9 (Perth and Kinross): 1 operational. The largest scheme is Griffin Wind farm (156 MW wind farm, operational since 28 February 2012), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of PH9

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Griffin Wind farmwind farmwind farm156operationalupdated Feb 2012Apr 2004granted Jan 2008Feb 2012Perth and Kinross7.9

Distance from the average position of the PH9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm100100

MW in pipeline: pending, approved and under-construction capacity.

How Perth and Kinross decides solar, wind and battery applications

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in Perth and Kinross

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.