Energy Projects Near You

Solar, wind and battery projects near Pitlochry (PH16)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH16 (Perth and Kinross): 1 approved but not yet running, 2 operational. The largest live scheme is Killiecrankie Waste Water Treatment Works (0.3 MW rooftop solar, approved on 16 January 2023, not yet built; REPD status may be out of date), 4.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
1approved, not running
2operational

Projects within 10 km of PH16

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Calliacharwind farmwind farm32.2operationalupdated Dec 2013Feb 2004granted Sep 2007Dec 2013Perth and Kinross9.8
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Killiecrankie Waste Water Treatment Worksrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Jan 2023Dec 2022granted Jan 2023Jan 2023Perth and Kinross4.9
Blair Castle Caravan Park, Blair Atholl Solar Farmsolar farmsolar farm0.2operationalupdated Jul 2023Jun 2023granted Jul 2023Jul 2023Perth and Kinross7.2

Distance from the average position of the PH16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100100
Rooftop solar101000.3
Wind farm100100

MW in pipeline: pending, approved and under-construction capacity.

How Perth and Kinross decides solar, wind and battery applications

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in Perth and Kinross

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PH16, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.