Energy Projects Near You

Solar, wind and battery projects near Bridge of Gaur (PH17)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH17 (Perth and Kinross): none of them is pending, approved or operational. The largest scheme is Rannoch Wind Farm (75 MW wind farm, application withdrawn on 9 June 2010), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of PH17

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rannoch Wind Farmwind farmwind farm75application withdrawnupdated Jun 2010——Jun 2010—6.4
Talladh-a-Bheithe Wind Farmwind farmwind farm75application withdrawnupdated Nov 2015Jun 2014—Nov 2015—6.4

Distance from the average position of the PH17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm200000

MW in pipeline: pending, approved and under-construction capacity.

How Perth and Kinross decides solar, wind and battery applications

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in Perth and Kinross

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.