Talladh-a-Bheithe Wind Farm (75 MW)

Talladh-a-Bheithe Wind Farm is a 75 MW wind farm project in Tayside, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 30 October 2015; the record was last updated on 3 November 2015. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

75 MWwind farm
application withdrawnstatus in REPD
3 November 2015record last updated
Scotlandcouncil area

Planning timeline

DateStage
23 June 2014Application submitted
30 October 2015Application withdrawn

Project details

Technology
wind farm
Capacity
75 MW
Status (REPD)
application withdrawn
Record last updated
3 November 2015
Operator or applicant
Eventus Duurzaam
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
24
Address (REPD)
Craiganour Estate 9km North-West of Kinloch Rannoch and 22km South of Dalwhinnie
Council area (by location)
not known
REPD reference
4616

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Rannoch Wind Farmwind farm75application withdrawn<0.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.7398, -4.3387).