Creag A Bhaird (29.9 MW wind farm)

Creag A Bhaird is a 29.9 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 September 2015; the record was last updated on 20 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWwind farm
refused on appealstatus in REPD
20 July 2015record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
6 February 2014Application submitted
20 March 2015Refused by the planning authority
16 June 2015Appeal lodged
10 September 2015Appeal refused

Project details

Technology
wind farm
Capacity
29.9 MW
Status (REPD)
refused on appeal
Record last updated
20 July 2015
Operator or applicant
Force 9 Energy Partners LLP And EDF Energy ER
Planning authority
Perth and Kinross
Planning application reference
13/02362/FLM
Appeal reference
PPA-340-2097
Turbines
13
Turbine height
115 m
Address (REPD)
Creag A' Bhaird Wind Farm Amulree
Council area (by location)
Perth and Kinross
Time to decision
58 weeks
REPD reference
4568

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Griffin Wind farmwind farm156operational4.2
Wind Farm at Meall Dearg Wind Farmwind farm147application submitted4.8
North Calliachar Wind Farmwind farm21abandoned8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5442, -3.7444).